RESS 4 auction results

27 projects were successful, for 1333.64 MW. A further 512.91 MW was offered and not successful. Results published 27th September 2024.

Weighted average strike pricePrice
All projects€96.85/MWh
Solar€104.76/MWh
Wind€90.47/MWh

Successful projects

ProjectCompanyTechnologyMW
Leacht Cross Solar Amarenco Solar Carrigaline LTD Solar 4.95
Ballynacrusha Solar Amarenco Solar Cobh LTD Solar 4.95
Garryndruig Solar Amarenco Solar Timoleague LTD Solar 4.95
Ballinrea Solar Park Ballinrea Solar Farm LTD Solar 55.0
Monroe East Solar Farm Franklink LTD Solar 8.0
Johnstown North PV Johnstown North Solar Limited Solar 22.0
Garr Solar and Storage OBM Solar Limited Solar 85.0
Barnacurragh Solar Park Tuam Energy Park Limited Solar 32.0
Drombeg Solar Park Phase II Tullamore Solar Farm Limited Solar 44.0
Milltown Solar Harmony Solar Meath Limited Solar 100.0
Grangeford Solar PV PRT Solar Limited Solar 48.0
Cuilmore Solar Park Cuilmore Solar Limited Solar 40.0
Treascon Solar Farm Blue Pine Solar 11 Limited Solar 60.0
Ballingaddy Solar Amarenco Solar Ennistymon LTD Solar 4.99
Carrigogna Solar Amarenco Solar Midleton LTD Solar 10.0
Dromroe Solar Array Grasstail Limited Solar 4.0
Killoran Solar PV Farm Soleirtricity Lisheen Limited Solar 76.0
Carrownagowan Wind Farm Futurenergy Carrownagowan DAC Onshore Wind 91.2
Drumnahough Wind Farm Drumnahough Wind Farm Designated Activity Company Onshore Wind 60.0
Upperchurch Wind Farm Upperchurch Windfarm Limited Onshore Wind 84.0
Taduff Solar Park TDC Community Solar Park Limited Solar 75.0
Clonymeath Solar Clonymeath Solar Limited Solar 63.0
Castlebanny Wind Farm Springfield Renewables Limited Onshore Wind 138.6
Kilcush Solar Farm Kilcush Solar Farm LTD Solar 50.0
Tullabeg Phase 2 Tullabeg Solar Farm 2 Limited Solar 105.0
Barnaleen Solar Farm Power Capital Developments Limited Solar 55.0
Barryscourt Solar Farm Barryscourt Solar Limited Solar 8.0

Source: EirGrid, RESS 4 Final Auction Results. The project rows sum to 1333.64 MW, which is the total EirGrid states in the same document. Company and project names are printed as EirGrid publishes them. These awards are not matched to planning applications on this site — see why.