Renewable energy projects near Shannon

Solar, wind and battery applications in the planning register for Shannon and the townlands around it, with the nearest substation and the capacity it has available. Last checked Sep 1, 2026.

8
Projects here
7
Still live
not refused, withdrawn or lapsed
14.2
MW stated
from 2 applications that state one
27.7
Hectares of site area
across 7 applications

The map plots 8 projects on a background supplied by OpenStreetMap, which receives your IP address when it loads.

Planning status

Planning status near Shannon Permission granted 7 Withdrawn 1

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.

Every application here

Solar — Shannon

Permission granted 1.2 MW stated6.875 ha siteLodged Jun 7, 2024 Ref 2460273
Grid: SHANNON (38 kV), 1.09 km away. 14.9 MW of firm generation capacity available at SHANNON.

Solar — Shannon

Permission granted Capacity not stated4.384 ha siteLodged Jan 29, 2026 Ref 2660039
Grid: SHANNON (38 kV), 0.71 km away. 14.9 MW of firm generation capacity available at SHANNON.

Solar — Shannon

Permission granted Capacity not stated3.85 ha siteLodged Mar 6, 2025 Ref 2560104
Grid: RINEANNA (38 kV), 0.71 km away. 14.9 MW of firm generation capacity available at SHANNON.

Solar — Shannon

Permission granted Capacity not stated3.67 ha siteLodged Mar 28, 2024 Ref 2460141
Grid: DRUMLINE (110 kV), 0.41 km away. 14.9 MW of firm generation capacity available at SHANNON.

Solar — Shannon

Permission granted Capacity not stated3.34 ha siteLodged Apr 28, 2025 Ref 2560218
Grid: RINEANNA (38 kV), 0.27 km away. 14.9 MW of firm generation capacity available at SHANNON.

Solar — Shannon

Permission granted Capacity not stated2.29 ha siteLodged Feb 14, 2025 Ref 2560064
Grid: RINEANNA (38 kV), 0.24 km away. 14.9 MW of firm generation capacity available at SHANNON.

Battery storage + Solar — Shannon

Permission granted 13.0 MW statedLodged Feb 1, 2022 Ref 2265
Grid: DRUMLINE (110 kV), 0.51 km away. 14.9 MW of firm generation capacity available at SHANNON.

Solar — Shannon

Withdrawn Capacity not stated3.34 ha siteLodged Feb 13, 2025 Ref 2560059
Grid: RINEANNA (38 kV), 0.27 km away. 14.9 MW of firm generation capacity available at SHANNON.

Areas are derived from the address as published by the planning authority or, for a direct application, by An Coimisiun Pleanala. A project on the boundary between two places may appear under either.

← All of County Clare