Renewable energy projects near Cloyne

Solar, wind and battery applications in the planning register for Cloyne and the townlands around it, with the nearest substation and the capacity it has available. Last checked Sep 1, 2026.

5
Projects here
2
Still live
not refused, withdrawn or lapsed
20.7
MW stated
from 4 applications that state one
27.5
Hectares of site area
across 2 applications

The map plots 5 projects on a background supplied by OpenStreetMap, which receives your IP address when it loads.

Planning status

Planning status near Cloyne Permission granted 2 Withdrawn 1 No decision recorded 2

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.

Every application here

Solar + Wind — Cloyne

Permission granted 5.7 MW stated13.95 ha siteLodged May 25, 2016 Ref 16/5269
Grid: CLOYNE (38 kV), 4.3 km away. No firm generation capacity currently available at CLOYNE.

Solar — Cloyne

Permission granted 5.0 MW statedLodged Apr 9, 2019 Ref 19/4869
Grid: CLOYNE (38 kV), 0.18 km away. No firm generation capacity currently available at CLOYNE.

Solar — Cloyne

No decision recorded Capacity not stated13.6 ha siteLodged Jun 19, 2026 Ref 26/1641
Grid: CLOYNE (38 kV), 1.29 km away. No firm generation capacity currently available at CLOYNE.

Solar — Cloyne

Withdrawn 5.0 MW statedLodged Dec 8, 2015 Ref 15/6768
Grid: CLOYNE (38 kV), 0.84 km away. No firm generation capacity currently available at CLOYNE.

Solar — Cloyne

No decision recorded 5.0 MW statedLodged Feb 26, 2019 Ref 19/4451
Grid: CLOYNE (38 kV), 0.18 km away. No firm generation capacity currently available at CLOYNE.

Areas are derived from the address as published by the planning authority or, for a direct application, by An Coimisiun Pleanala. A project on the boundary between two places may appear under either.

← All of County Cork