Solar, wind and battery applications in the planning register for
Midleton and the townlands around it, with the nearest substation and the
capacity it has available. Last checked Sep 1, 2026.
9
Projects here
8
Still live
not refused, withdrawn or lapsed
10.0
MW stated
from 1 application that state one
66.3
Hectares of site area
across 3 applications
The map plots 9 projects on a background supplied by
OpenStreetMap, which receives your IP address when it loads.
Planning status
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the
large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as
they move through planning, and which substations still have capacity to take a connection. If you
want to be told when something is lodged near your land, leave an email address.
No decision recordedCapacity not statedLodged Sep 23, 2021Ref 21/6612
Grid: MIDLETON (110 kV), 1.29 km away.
20.1 MW of firm generation capacity available at MIDLETON.
Areas are derived from the address as published by the planning authority
or, for a direct application, by An Coimisiun Pleanala. A project on the boundary between two