Renewable energy projects near Naas

Solar, wind and battery applications in the planning register for Naas and the townlands around it, with the nearest substation and the capacity it has available. Last checked Sep 1, 2026.

26
Projects here
13
Still live
not refused, withdrawn or lapsed
105.0
MW stated
from 1 application that state one
717.7
Hectares of site area
across 23 applications

The map plots 26 projects on a background supplied by OpenStreetMap, which receives your IP address when it loads.

Planning status

Planning status near Naas Under appeal 2 Permission granted 11 Withdrawn 1 Permission lapsed 4 No decision recorded 8

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.

Every application here

Solar — Naas

Under appeal 105.0 MW stated128.6 ha siteLodged Feb 2, 2024 Ref 2460079
Grid: DUNSTOWN (400 kV), 2.58 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

Permission granted Capacity not stated38.08 ha siteLodged Aug 6, 2019 Ref 19888
Grid: DUNFIRTH (38 kV), 2.64 km away. No firm generation capacity currently available at DUNFIRTH.

Battery storage + Solar + Wind — Naas

Under appeal Capacity not stated37.51 ha siteLodged Aug 13, 2024 Ref 2460787
Grid: NAAS (38 kV), 3.18 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

Permission granted Capacity not stated10.8 ha siteLodged Nov 24, 2020 Ref 201418
Grid: MONREAD (110 kV), 0.38 km away. 17.5 MW of firm generation capacity available at MONREAD.

Solar — Naas

Permission granted Capacity not stated10.8 ha siteLodged Feb 21, 2025 Ref 2560166
Grid: MONREAD (110 kV), 0.36 km away. 17.5 MW of firm generation capacity available at MONREAD.

Solar — Naas

Permission granted Capacity not stated7.79 ha siteLodged Jun 21, 2023 Ref 23683
Grid: MONREAD (110 kV), 0.27 km away. 17.5 MW of firm generation capacity available at MONREAD.

Solar — Naas

Permission granted Capacity not stated5.0 ha siteLodged Jul 25, 2024 Ref 2460715
Grid: BARODA (110 kV), 1.99 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

Permission granted Capacity not stated4.35 ha siteLodged Aug 5, 2022 Ref 22969
Grid: NAAS (38 kV), 1.77 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

Permission granted Capacity not stated4.2 ha siteLodged Nov 24, 2023 Ref 2360410
Grid: BARODA (110 kV), 2.26 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

Permission granted Capacity not stated3.56 ha siteLodged Oct 27, 2024 Ref 2461126
Grid: SALLINS (38 kV), 5.01 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

Permission granted Capacity not stated2.54 ha siteLodged Aug 22, 2022 Ref 221026
Grid: MONREAD (110 kV), 1.08 km away. 17.5 MW of firm generation capacity available at MONREAD.

Solar — Naas

Permission granted Capacity not stated2.26 ha siteLodged Sep 20, 2023 Ref 2360230
Grid: BARODA (110 kV), 2.8 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

Permission granted Capacity not stated0.192 ha siteLodged Feb 21, 2025 Ref 2560167
Grid: MONREAD (110 kV), 0.3 km away. 17.5 MW of firm generation capacity available at MONREAD.

Solar — Naas

No decision recorded Capacity not stated128.6 ha siteLodged Dec 22, 2023 Ref 2360539
Grid: DUNSTOWN (400 kV), 3.03 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

No decision recorded Capacity not stated128.6 ha siteLodged Jan 27, 2024 Ref 2460049
Grid: DUNSTOWN (400 kV), 3.32 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar + Wind — Naas

Permission lapsed Capacity not stated62.33 ha siteLodged Aug 28, 2019 Ref 19971
Grid: GRIFFINRATH (110 kV), 2.86 km away. 2.6 MW of firm generation capacity available at GRIFFINRATH.

Solar — Naas

No decision recorded Capacity not stated38.08 ha siteLodged Jun 14, 2019 Ref 19676
Grid: DUNFIRTH (38 kV), 2.56 km away. No firm generation capacity currently available at DUNFIRTH.

Solar — Naas

Permission lapsed Capacity not stated38.08 ha siteLodged Jul 16, 2020 Ref 20770
Grid: DUNFIRTH (38 kV), 2.73 km away. No firm generation capacity currently available at DUNFIRTH.

Battery storage + Solar + Wind — Naas

No decision recorded Capacity not stated37.51 ha siteLodged Aug 1, 2024 Ref 2460740
Grid: NAAS (38 kV), 3.13 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

Withdrawn Capacity not stated16.08 ha siteLodged Dec 22, 2017 Ref 171494
Grid: DUNFIRTH (38 kV), 2.79 km away. No firm generation capacity currently available at DUNFIRTH.

Solar — Naas

Permission lapsed Capacity not stated7.79 ha siteLodged Jul 16, 2020 Ref 20769
Grid: MONREAD (110 kV), 0.23 km away. 17.5 MW of firm generation capacity available at MONREAD.

Solar — Naas

No decision recorded Capacity not stated4.2 ha siteLodged Nov 22, 2023 Ref 2360403
Grid: BARODA (110 kV), 1.96 km away. 5.1 MW of firm generation capacity available at NAAS.

Solar — Naas

Permission lapsed Capacity not stated0.779 ha siteLodged Apr 24, 2017 Ref 17463
Grid: MONREAD (110 kV), 0.31 km away. 17.5 MW of firm generation capacity available at MONREAD.

Solar — Naas

No decision recorded Capacity not statedLodged Nov 13, 2020 Ref 201365
Grid: MONREAD (110 kV), 0.38 km away. 17.5 MW of firm generation capacity available at MONREAD.

Solar — Naas

No decision recorded Capacity not statedLodged May 19, 2023 Ref 23538
Grid: MONREAD (110 kV), 0.25 km away. 17.5 MW of firm generation capacity available at MONREAD.

Solar — Naas

No decision recorded Capacity not statedLodged Jun 9, 2023 Ref 23619
Grid: MONREAD (110 kV), 0.29 km away. 17.5 MW of firm generation capacity available at MONREAD.

Areas are derived from the address as published by the planning authority or, for a direct application, by An Coimisiun Pleanala. A project on the boundary between two places may appear under either.

← All of County Kildare