Solar, wind and battery applications in the planning register for
Summerhill and the townlands around it, with the nearest substation and the
capacity it has available. Last checked Sep 1, 2026.
7
Projects here
5
Still live
not refused, withdrawn or lapsed
8.0
MW stated
from 1 application that state one
584.2
Hectares of site area
across 7 applications
The map plots 7 projects on a background supplied by
OpenStreetMap, which receives your IP address when it loads.
Planning status
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the
large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as
they move through planning, and which substations still have capacity to take a connection. If you
want to be told when something is lodged near your land, leave an email address.
Permission lapsed8.0 MW stated23.6 ha siteLodged Jul 3, 2017Ref RA170766
Grid: CLARKSTOWN (38 kV), 0.54 km away.
2.6 MW of firm generation capacity available at CLARKSTOWN.
Areas are derived from the address as published by the planning authority
or, for a direct application, by An Coimisiun Pleanala. A project on the boundary between two
places may appear under either.