Solar at Avoca
Ballycooleen , Avoca , Co. Wicklow
Grid
Association: Matched to AVOCA on place name and proximity (4.02 km).
Available capacity: ESB Networks has not published available generation capacity for AVOCA.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | Mar 20, 2026 |
|---|---|
| Decision due | May 14, 2026 |
| Decision made | Apr 30, 2026 |
| Permission expires | Jan 10, 2028 |
| Decision | UNCONDITIONAL |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Wicklow County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.