Wind at Ballindown
STONESTOWN KILCAMIN CRANCREAGH , DERRINLOUGH AND BALLINDOWN , CO. OFFALY
Grid
Association: No confident match to a named grid station.
Available capacity: 4.2 MW of firm generation capacity available at LUMCLOON.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | Aug 15, 2019 |
|---|---|
| Further information requested | Oct 9, 2019 |
| Further information received | Dec 6, 2019 |
| Decision due | Mar 12, 2020 |
| Decision made | Mar 12, 2020 |
| Permission granted | Nov 23, 2020 |
| Appeal submitted | Jun 2, 2020 |
| Permission expires | Oct 26, 2026 |
| Decision | CONDITIONAL |
| Appeal reference | 307266 20 |
| Appeal decision | WITHDRAWN |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Offaly County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.