Battery storage at Ballygeery West

Ballygeery West , Co. Clare

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
6.2
Site area (hectares)
Battery storage
Technology

Grid

Nearest substation: PROSPECT (220 kV), 0.12 km away.
Association: Nothing states a connection point and the place name does not match a station, but PROSPECT is only 0.12 km away — close enough that it is usually, though not always, where a project like this connects. Counted separately from the match rate.
Available capacity: ESB Networks has not published available generation capacity for PROSPECT.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedSep 22, 2023
Further information requestedNov 14, 2023
Further information receivedAug 20, 2024
Decision dueOct 23, 2024
Decision madeOct 22, 2024
Permission grantedNov 26, 2024
Permission expiresNov 25, 2034
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Clare County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.