Wind at Ballyhubert
Pollymount Bellanamullia Scramoge , Treanaceeve and Ballyhubert , County Roscommon.
Grid
Association: The application names SLIABH BAWN as its connection point.
Available capacity: ESB Networks has not published available generation capacity for SLIABH BAWN.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | Sep 15, 2025 |
|---|---|
| Further information requested | Dec 23, 2025 |
| Further information received | Jun 5, 2026 |
| Decision due | Aug 20, 2026 |
| Decision made | Aug 20, 2026 |
| Decision | CONDITIONAL |
What we have seen change
- — status: submitted → granted, decision: N/A → CONDITIONAL
Recorded by this tracker each time the register was checked. It begins when we first observed the application, not when the application was made.
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Roscommon County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.