Solar at Ballynaguilsha

BALLINDOWN BOGDERRIESBALLYWILLIAM , AND BALLYNAGUILSHA , CO OFFALY

Withdrawn
Planning status
40.0
Capacity
as stated in the application
70.2
Site area (hectares)
Solar
Technology

Grid

Nearest substation: BIRR (38 kV), 3.45 km away.
Association: No confident match to a named grid station.
Available capacity: 4.4 MW of firm generation capacity available at BIRR.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedJun 16, 2020
Further information requestedAug 7, 2020
Further information receivedOct 13, 2020
WithdrawnMar 2, 2021
DecisionN/A

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Offaly County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.