Grid
Association: Matched to CASTLETROY on place name and proximity (0.1 km).
Available capacity: 5.8 MW of firm generation capacity available at CASTLETROY.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | Apr 16, 2025 |
|---|---|
| Further information requested | Jun 9, 2025 |
| Further information received | Jul 28, 2025 |
| Decision due | Sep 24, 2025 |
| Decision made | Sep 23, 2025 |
| Permission granted | Oct 28, 2025 |
| Permission expires | Oct 27, 2030 |
| Decision | CONDITIONAL |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Limerick County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.