Solar at Clondoolusk

TOWNLANDS OF TRASCAN AND CLONDOOLUSK , CO. OFFALY

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
39.23
Site area (hectares)
Solar
Technology

Grid

Nearest substation: PORTARLINGTON (38 kV), 4 km away.
Association: No confident match to a named grid station.
Available capacity: 4.1 MW of firm generation capacity available at PORTARLINGTON.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedAug 5, 2022
Further information requestedSep 29, 2022
Further information receivedJul 6, 2023
Decision dueOct 18, 2023
Decision madeOct 18, 2023
Appeal submittedNov 10, 2023
Appeal decidedJul 15, 2024
Permission expiresJul 14, 2029
DecisionCONDITIONAL
Appeal referenceABP - 318436-23
Appeal decisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Offaly County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.