Permission granted
Planning status
100.0
Capacity
as stated in the application
121.5
Site area (hectares)
Solar
Technology

Grid

Nearest substation: EDENDERRY (38 kV), 1.25 km away.
Association: Nothing states a connection point and the place name does not match a station, but EDENDERRY is only 1.25 km away — close enough that it is usually, though not always, where a project like this connects. Counted separately from the match rate.
Available capacity: 10.8 MW of firm generation capacity available at EDENDERRY.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedMar 25, 2022
Further information requestedMay 19, 2022
Further information receivedJul 29, 2022
Decision dueSep 22, 2022
Decision madeSep 21, 2022
Permission grantedNov 11, 2022
Permission expiresNov 10, 2032
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Kildare County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.