Battery storage + Solar at Crackenstown
Doghtog & Crackenstown , Co. Meath
Grid
Association: No confident match to a named grid station.
Available capacity: 2.3 MW of firm generation capacity available at BALTRASNA.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | Aug 4, 2020 |
|---|---|
| Further information requested | Sep 25, 2020 |
| Further information received | Nov 25, 2020 |
| Decision due | Dec 22, 2020 |
| Decision made | Dec 16, 2020 |
| Permission granted | Feb 4, 2021 |
| Permission expires | Feb 3, 2031 |
| Decision | CONDITIONAL |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Meath County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.