Battery storage at Dubli

a c. 1.7 ha site located within the ESB Inchicore substation site, specifically lands south of Kylemore Way and northwest of the existing ESB Substation, Kylemore Way, Dublin 8, D08 and to the immediate west of the Kylemore BESS, Kylemore Road, Dubli

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
2.030954
Site area (hectares)
Battery storage
Technology

Grid

Nearest substation: INCHICORE (110 kV), 0.21 km away.
Association: Matched to INCHICORE on place name and proximity (0.21 km).
Available capacity: 315.1 MW of firm generation capacity available at INCHICORE.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedMay 30, 2025
Further information requestedJul 24, 2025
Further information receivedAug 1, 2025
Decision dueAug 28, 2025
Decision madeAug 28, 2025
Permission grantedOct 2, 2025
DecisionGRANT PERMISSION

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Dublin City Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.