Solar at Edenderry

BALLINOWLART NORTH BALLYKILLEN KILCUMBER CLONCANT AND CUSHALING , EDENDERRY , CO. OFFALY

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
117.4
Site area (hectares)
Solar
Technology

Grid

Nearest substation: CUSHALING (110 kV), 0.38 km away.
Association: Matched to CUSHALING on place name and proximity (0.38 km).
Available capacity: ESB Networks has not published available generation capacity for CUSHALING.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedSep 30, 2021
Further information requestedMar 21, 2022
Further information receivedAug 16, 2022
Decision dueSep 19, 2022
Decision madeSep 19, 2022
Permission grantedOct 26, 2022
Permission expiresOct 25, 2032
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Offaly County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.