Solar at Enfield

Ovidstown Development Site , Ballyvoneen , Enfield

Permission lapsed
Planning status
Not stated
Capacity
the application states no figure in MW
13.6
Site area (hectares)
Solar
Technology

Grid

Nearest substation: DUNFIRTH (38 kV), 2.21 km away.
Association: No confident match to a named grid station.
Available capacity: No firm generation capacity currently available at DUNFIRTH.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedFeb 1, 2018
Further information requestedMar 27, 2018
Further information receivedDec 18, 2018
Decision dueJan 23, 2019
Decision madeJan 23, 2019
Permission grantedFeb 27, 2019
Permission expiresFeb 26, 2024
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Kildare County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.