Solar at Ennis

Ballyvonnavaum TD Coolshamroge TD Cloonmore TD Deerpark TD , and Manusmore TD , Ennis Co Clare

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
Not published
Site area (hectares)
Solar
Technology

Grid

Nearest substation: CLARECASTLE (38 kV), 4.42 km away.
Association: Matched to ENNIS on place name and proximity (5.53 km).
Available capacity: 15.1 MW of firm generation capacity available at ENNIS.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedJul 1, 2022
Further information requestedAug 24, 2022
Further information receivedDec 15, 2022
Decision dueMar 9, 2023
Decision madeMar 9, 2023
Permission grantedApr 14, 2023
Permission expiresApr 13, 2033
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Clare County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.