Solar at Glenlon South

Land to the west/north-west of Ardnacrusha , within the townlands of Castlebank , and Glenlon South.

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
5.52
Site area (hectares)
Solar
Technology

Grid

Nearest substation: ARDNACRUSHA (110 kV), 0.8 km away.
Association: Matched to ARDNACRUSHA on place name and proximity (0.8 km).
Available capacity: 35 MW of firm generation capacity available at ARDNACRUSHA.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedSep 16, 2025
Decision dueDec 24, 2025
Decision madeDec 16, 2025
Permission grantedJan 27, 2026
Permission expiresOct 9, 2028
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Clare County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.