Solar at Inniscarra

Garravagh , Inniscarra , Cork

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
2.64
Site area (hectares)
Solar
Technology

Grid

Nearest substation: COOLROE (110 kV), 0.7 km away.
Association: The application names COOLROE as its connection point.
Available capacity: 25.5 MW of firm generation capacity available at COOLROE.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedJun 18, 2021
Decision dueAug 12, 2021
Decision madeAug 12, 2021
Permission grantedMar 10, 2022
Appeal submittedSep 3, 2021
Appeal decidedMar 10, 2022
DecisionCONDITIONAL
Appeal referenceABP-311292-21
Appeal decisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Cork City Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.