Wind at Killoneen
Clonarrow or Riverlyons , and Killoneen , Co. Offaly.
Grid
Association: No confident match to a named grid station.
Available capacity: ESB Networks has not published available generation capacity for MOUNT LUCAS.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | May 23, 2025 |
|---|---|
| Further information requested | Jul 17, 2025 |
| Further information received | Nov 28, 2025 |
| Decision due | Jan 31, 2026 |
| Decision made | Jan 30, 2026 |
| Permission granted | Mar 12, 2026 |
| Permission expires | Mar 11, 2036 |
| Decision | CONDITIONAL |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Offaly County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.