Solar at Kilnaglory

Kilnaglory Lisheens Greenfield Co.Cork

This application's address does not name a town or townland, so it is listed under Kilnaglory because that is the nearest area we track — 0.3 km away. That is a distance we measured, not a location the planning record states.

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
Not published
Site area (hectares)
Solar
Technology

Grid

Nearest substation: BALLINCOLLIG (38 kV), 0.35 km away.
Association: The application names BALLINCOLLIG as its connection point.
Available capacity: 10.5 MW of firm generation capacity available at BALLINCOLLIG.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedJul 15, 2022
Decision dueNov 14, 2022
Decision madeNov 10, 2022
Permission grantedDec 13, 2022
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Cork County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.