Solar at Leixlip

Leixlip Demesne , Leixlip , Co. Kildare

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
14.324
Site area (hectares)
Solar
Technology

Grid

Nearest substation: LEIXLIP GENERATOR (38 kV), 0.64 km away.
Association: Matched to LEIXLIP GENERATOR on place name and proximity (0.64 km).
Available capacity: ESB Networks has not published available generation capacity for LEIXLIP GENERATOR.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedMay 12, 2023
Further information requestedJul 5, 2023
Further information receivedJul 12, 2023
Decision dueAug 8, 2023
Decision madeAug 4, 2023
Permission grantedDec 18, 2023
Appeal submittedAug 31, 2023
Appeal decidedDec 18, 2023
Permission expiresDec 17, 2028
DecisionCONDITIONAL
Appeal referenceABP 317923-23
Appeal decisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Kildare County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.