Wind at Letterkenny

LISTILLION LURGY KNOCKBRACK AGHLEHARD TREANAVINNY GLENMAQUIN LOWER KINCRAIGY ROOSKEY LISCLAMERTY CARRICKNAMART MONDOOEY UPPER MONDOOEY MIDDLE BALLYHOLEY FAR DRUMATOLAND SHESKINAPOLL CARRICKADAWSON WOODLAND AND MOMEEN , LETTERKENNY , CO DONEGAL

Permission lapsed
Planning status
Not stated
Capacity
the application states no figure in MW
Not published
Site area (hectares)
Wind
Technology

Grid

Nearest substation: LETTERKENNY (110 kV), 5.02 km away.
Association: The application names LETTERKENNY as its connection point.
Available capacity: No firm generation capacity currently available at LETTERKENNY.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedDec 18, 2020
Decision dueFeb 20, 2021
Decision madeFeb 11, 2021
Permission expiresMar 28, 2026
DecisionUNCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Donegal County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.