Wind at Mullagharlin Dundalk
Wuxi Biologics Ireland Limited , Dundalk Science And Technology Park , Mullagharlin Dundalk
Grid
Association: Matched to MULLAGHARLIN on place name and proximity (0.68 km).
Available capacity: 27.1 MW of firm generation capacity available at MULLAGHARLIN.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | Sep 15, 2023 |
|---|---|
| Further information requested | Nov 3, 2023 |
| Further information received | Jun 26, 2024 |
| Decision due | Jul 23, 2024 |
| Decision made | Jul 18, 2024 |
| Appeal submitted | Aug 13, 2024 |
| Appeal decided | Feb 25, 2025 |
| Permission expires | Feb 24, 2030 |
| Decision | CONDITIONAL |
| Appeal reference | ABP 320542-24 |
| Appeal decision | CONDITIONAL |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Louth County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.