Solar at Parkmore

CLONBEALE BEG GLEBE RATHURE NORTH (PARCEL 1) AND PARKMORE (PARCEL 2) , CO. OFFALY

This application's address does not name a town or townland, so it is listed under Parkmore because that is the nearest area we track — 0.5 km away. That is a distance we measured, not a location the planning record states.

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
69.0
Site area (hectares)
Solar
Technology

Grid

Nearest substation: BIRR (38 kV), 6.72 km away.
Association: No confident match to a named grid station.
Available capacity: 4.4 MW of firm generation capacity available at BIRR.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedJul 22, 2022
Further information requestedSep 15, 2022
Further information receivedMay 24, 2023
Decision dueJun 20, 2023
Decision madeJun 20, 2023
Permission grantedJul 25, 2023
Permission expiresJul 24, 2033
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Offaly County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.