Wind at Tawnadremira

Dunneill Wind Farm , Located in the townland Crowagh or Dunneill Mountain , Ballyglass (ED Dromore) and Tawnadremira

Permission granted
Planning status
0.85
Capacity
as stated in the application
Not published
Site area (hectares)
Wind
Technology

Grid

Nearest substation: GLENREE (110 kV), 14.76 km away.
Association: No confident match to a named grid station.
Available capacity: 2.2 MW of firm generation capacity available at GLENREE.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedAug 26, 2022
Further information requestedOct 20, 2022
Further information receivedMar 2, 2023
Decision dueApr 26, 2023
Decision madeApr 25, 2023
Permission grantedJun 2, 2023
Permission expiresOct 23, 2039
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Sligo County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.