Solar at Thomastown Demesne South
Rathduff , Thomastown Demesne South , Co. Tipperary
Grid
Association: No confident match to a named grid station.
Available capacity: 8.1 MW of firm generation capacity available at TIPPERARY.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | Jul 13, 2021 |
|---|---|
| Further information requested | Sep 3, 2021 |
| Further information received | Mar 9, 2022 |
| Decision due | Apr 5, 2022 |
| Decision made | Mar 31, 2022 |
| Appeal submitted | Apr 26, 2022 |
| Appeal decided | Sep 24, 2024 |
| Permission expires | Sep 23, 2029 |
| Decision | CONDITIONAL |
| Appeal reference | ABP-313424-22 |
| Appeal decision | CONDITIONAL |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Tipperary County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.