Renewable energy projects in County Tipperary

Every solar, wind and battery application in the county's planning register, joined to the ESB Networks substation nearest it and the generation capacity that substation has available. Updated from public records; last checked Sep 1, 2026.

Enter an Eircode, or a town, village or townland name. Only the routing key — the first three characters — is used and it is never stored: that places you within a few kilometres of your town, which is all this needs, and Eircode's full address database is licensed and not public anyway. All 139 routing keys in the country are covered.

163
Utility-scale projects
solar, wind and battery
76
Still live in the system
not refused, withdrawn or lapsed
779.0
MW stated
from 20 of 163 applications that state one
6656.5
Hectares of site area
across 117 applications
39
Substations with no capacity
of 136 near these projects
1
Under appeal now
19 have been appealed at some point

Where they are

The map plots 163 projects on a background supplied by OpenStreetMap, which receives your IP address when it loads.

Positions are as published in the national planning register, or — for applications made directly to An Coimisiun Pleanala — at the centre of the site boundary that case publishes. Colour shows planning status.

Planning status

Planning status of renewable projects in County Tipperary Application submitted 6 Further information reque… 1 Under appeal 1 Permission granted 68 Permission refused 2 Withdrawn 6 Permission lapsed 16 No decision recorded 63

Technologies

Technologies in the County Tipperary pipeline Solar 117 Wind 36 Battery storage 31

A project appears under each technology it includes, so co-located solar-and-battery schemes are counted in both.

Grid capacity

74 of 163 projects are matched to a named substation with enough confidence to publish the link (45.4%). The remaining 89 are listed as unmatched rather than guessed — matching a project to the wrong substation is worse than leaving it unmatched, so a name match must also be corroborated by distance before it counts.

90 projects sit at a substation ESB Networks currently publishes as having no firm generation capacity available.

Areas

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.

Live applications

Wind — Lanespark

Application submitted LanesparkCapacity not stated1125.62 ha siteLodged Jun 15, 2026 Ref ABP-324370
Grid: GLENGOOLE (38 kV), 3.82 km away. No firm generation capacity currently available at GLENGOOLE.

Wind — Templemore

Permission granted TemplemoreCapacity not stated401.6 ha siteLodged Dec 14, 2023 Ref ABP-318704
Grid: TEMPLEMORE (38 kV), 3.48 km away. No firm generation capacity currently available at TEMPLEMORE.

Wind — Cronekill

Application submitted CronekillCapacity not stated365.57 ha siteLodged May 8, 2026 Ref ABP-324279
Grid: BIRR (38 kV), 6.43 km away. 4.4 MW of firm generation capacity available at BIRR.

Solar — Roscrea

Permission granted RoscreaCapacity not stated352.6 ha siteLodged Mar 3, 2021 Ref 21261
Grid: IKERRIN (110 kV), 4.52 km away. No firm generation capacity currently available at ROSCREA.

Wind — Ballygammane

Permission granted BallygammaneCapacity not stated330.68 ha siteLodged Dec 12, 2024 Ref ABP-321454
Grid: LOUGHTAGALLA (38 kV), 3.6 km away. No firm generation capacity currently available at LOUGHTAGALLA.

Solar — Graigue

Permission granted GraigueCapacity not stated222.2 ha siteLodged Jan 3, 2025 Ref 2560003
Grid: HOLYCROSS ROAD (38 kV), 5.49 km away. No firm generation capacity currently available at HOLYCROSS ROAD.

Solar — Cashel

Application submitted CashelCapacity not stated151.0 ha siteLodged Aug 28, 2026 Ref 2660834
Grid: CASHEL (38 kV), 2.1 km away. No firm generation capacity currently available at CASHEL.

Solar — Roscrea

Permission granted RoscreaCapacity not stated142.7 ha siteLodged Dec 6, 2022 Ref 22662
Grid: IKERRIN (110 kV), 4.28 km away. No firm generation capacity currently available at ROSCREA.

Solar — Dually

Permission granted DuallyCapacity not stated129.0 ha siteLodged Mar 4, 2024 Ref 2460156
Grid: CASHEL (38 kV), 3.89 km away. No firm generation capacity currently available at CASHEL.

Wind — Seskin

Permission granted SeskinCapacity not stated103.03 ha siteLodged May 7, 2021 Ref ABP-310171
Grid: SCREGGAN (110 kV), 5.38 km away. ESB Networks has not published available generation capacity for SCREGGAN.

Solar — Seskin

Permission granted SeskinCapacity not stated92.0 ha siteLodged Aug 16, 2022 Ref 2260420
Grid: CAUTEEN (110 kV), 0.39 km away. 8.1 MW of firm generation capacity available at CAUTEEN.

Solar — Nenagh

Permission granted NenaghCapacity not stated88.5 ha siteLodged Feb 7, 2024 Ref 2460074
Grid: TYONE (38 kV), 3.25 km away. 12.4 MW of firm generation capacity available at NENAGH.

Battery storage + Wind — Cornhill

Permission granted CornhillCapacity not stated78.91 ha siteLodged Sep 22, 2023 Ref 2360763
Grid: BIRR (38 kV), 8.08 km away. 4.4 MW of firm generation capacity available at DALLOW.

Solar — Killoran

Permission granted Killoran122.0 MW stated77.0 ha siteLodged Jul 30, 2021 Ref 211128
Grid: LISHEEN (110 kV), 0.99 km away. 20.5 MW of firm generation capacity available at LISHEEN.

Solar — Rathkeevin

Permission granted Rathkeevin60.0 MW stated66.95 ha siteLodged Jun 22, 2023 Ref 23172
Grid: LAWLESSTOWN (38 kV), 5.13 km away. No firm generation capacity currently available at LAWLESSTOWN.

Solar — Solloghod-More

Application submitted Solloghod-More53.1 MW stated65.9 ha siteLodged Jul 10, 2026 Ref 2660672
Grid: CAUTEEN (110 kV), 1.05 km away. 8.1 MW of firm generation capacity available at CAUTEEN.

Battery storage + Solar — Derrymore Roscrea

Permission granted Derrymore RoscreaCapacity not stated58.11 ha siteLodged Jan 20, 2023 Ref 2310
Grid: IKERRIN (110 kV), 2.75 km away. No firm generation capacity currently available at ROSCREA.

Solar — Donohill

Permission granted DonohillCapacity not stated54.5 ha siteLodged Feb 25, 2022 Ref 22165
Grid: CAUTEEN (110 kV), 2.14 km away. 8.1 MW of firm generation capacity available at CAUTEEN.

Solar — Thomastown Demesne South

Permission granted Thomastown Demesne SouthCapacity not stated42.68 ha siteLodged May 19, 2026 Ref 2660469
Grid: TIPPERARY (110 kV), 2.71 km away. 8.1 MW of firm generation capacity available at TIPPERARY.

Solar — Lisheennamalausa

Permission granted LisheennamalausaCapacity not stated39.0 ha siteLodged Jul 28, 2021 Ref 211109
Grid: CAUTEEN (110 kV), 1.04 km away. 8.1 MW of firm generation capacity available at CAUTEEN.

Wind — Mountphilips

Permission granted MountphilipsCapacity not stated37.19 ha siteLodged Dec 13, 2019 Ref ABP-306204
Grid: KNOCKANE (110 kV), 5.91 km away. ESB Networks has not published available generation capacity for KNOCKANE.

Wind — Nenagh

Further information requested NenaghCapacity not stated34.26 ha siteLodged May 29, 2026 Ref 2660534
Grid: NENAGH (110 kV), 5.58 km away. 12.4 MW of firm generation capacity available at NENAGH.

Solar — Roscrea

Permission granted RoscreaCapacity not stated34.11 ha siteLodged Aug 29, 2023 Ref 2360677
Grid: IKERRIN (110 kV), 2.91 km away. No firm generation capacity currently available at ROSCREA.

Solar — Roscrea

Application submitted RoscreaCapacity not stated34.11 ha siteLodged Jul 8, 2026 Ref 2660660
Grid: IKERRIN (110 kV), 2.91 km away. No firm generation capacity currently available at ROSCREA.

Solar — Cahir

Permission granted CahirCapacity not stated30.08 ha siteLodged Jul 19, 2022 Ref 2260376
Grid: CAHIR (110 kV), 0.59 km away. No firm generation capacity currently available at CAHIR.

Solar — Roscrea

Permission granted RoscreaCapacity not stated29.09 ha siteLodged Nov 28, 2019 Ref 19601323
Grid: IKERRIN (110 kV), 0.57 km away. No firm generation capacity currently available at ROSCREA.

Solar — Roscrea

Permission granted RoscreaCapacity not stated29.09 ha siteLodged Nov 28, 2022 Ref 22652
Grid: IKERRIN (110 kV), 0.57 km away. No firm generation capacity currently available at ROSCREA.

Solar — Nenagh

Permission granted NenaghCapacity not stated19.18 ha siteLodged Mar 16, 2022 Ref 22225
Grid: TYONE (38 kV), 1.38 km away. 12.4 MW of firm generation capacity available at NENAGH.

Solar — Gortdrum

Permission granted GortdrumCapacity not stated17.44 ha siteLodged Jan 5, 2024 Ref 2460006
Grid: CAUTEEN (110 kV), 2.63 km away. 8.1 MW of firm generation capacity available at CAUTEEN.

Solar — Clonmel

Permission granted ClonmelCapacity not stated15.9 ha siteLodged Feb 5, 2026 Ref 2660086
Grid: ARDGEEHA (38 kV), 1.09 km away. No firm generation capacity currently available at ARDGEEHA.

Solar — Donohill

Permission granted Donohill8.0 MW stated15.04 ha siteLodged May 2, 2017 Ref 17600456
Grid: CAUTEEN (110 kV), 1.07 km away. 8.1 MW of firm generation capacity available at CAUTEEN.

Solar — Derryville

Permission granted DerryvilleCapacity not stated13.75 ha siteLodged Jul 28, 2022 Ref 2260395
Grid: LISHEEN (110 kV), 2.05 km away. 20.5 MW of firm generation capacity available at LISHEEN.

Solar — Lacken Kilballygorman

Permission granted Lacken KilballygormanCapacity not stated12.5 ha siteLodged Apr 9, 2021 Ref 21473
Grid: ARDFINNAN (38 kV), 1.17 km away. No firm generation capacity currently available at ARDFINNAN.

Wind — Ballinvoher Redm

Permission granted Ballinvoher RedmCapacity not stated11.7 ha siteLodged Oct 9, 2025 Ref 2561016
Grid: CALLAN (38 kV), 11.1 km away. 1.2 MW of firm generation capacity available at CALLAN.

Solar — Ballynilard

Permission granted BallynilardCapacity not stated10.8 ha siteLodged Sep 25, 2023 Ref 2360765
Grid: KILROSS ROAD (38 kV), 0.66 km away. 4.6 MW of firm generation capacity available at KILROSS ROAD.

Solar — Holycross Road Thurles

Permission granted Holycross Road ThurlesCapacity not stated10.06 ha siteLodged Aug 30, 2023 Ref 2360682
Grid: HOLYCROSS ROAD (38 kV), 0.22 km away. No firm generation capacity currently available at HOLYCROSS ROAD.

Solar — Thurles

Permission granted ThurlesCapacity not stated9.3 ha siteLodged Dec 21, 2022 Ref 2260732
Grid: HOLYCROSS ROAD (38 kV), 0.53 km away. No firm generation capacity currently available at HOLYCROSS ROAD.

Battery storage + Solar — Carrick-On-Suir

Permission granted Carrick-On-Suir3.6 MW stated9.12 ha siteLodged Aug 23, 2017 Ref 17600928
Grid: DEERPARK (38 kV), 0.92 km away. 0.6 MW of firm generation capacity available at DEERPARK.

Battery storage + Solar — Carrick-On-Suir

Permission granted Carrick-On-SuirCapacity not stated9.12 ha siteLodged Dec 15, 2021 Ref 211819
Grid: DEERPARK (38 kV), 0.92 km away. 0.6 MW of firm generation capacity available at DEERPARK.

Solar — Golden

Permission granted GoldenCapacity not stated6.424 ha siteLodged Apr 30, 2025 Ref 2569
Grid: CASHEL (38 kV), 5.95 km away. No firm generation capacity currently available at CASHEL.