South Dublin
Renewable energy projects in South Dublin
Every solar, wind and battery application in the county's planning register,
joined to the ESB Networks substation nearest it and the generation capacity that substation
has available. Updated from public records; last checked Sep 1, 2026.
Find projects near you
Search
Enter an Eircode , or a town, village or townland name. Only the routing
key — the first three characters — is used and it is never stored: that places you within
a few kilometres of your town, which is all this needs, and Eircode's full address
database is licensed and not public anyway. All 139 routing keys in the
country are covered.
47
Utility-scale projects
solar, wind and battery
36
Still live in the system
not refused, withdrawn or lapsed
MW stated
from 0 of 47 applications that state one
353.4
Hectares of site area
across 47 applications
4
Substations with no capacity
of 189 near these projects
0
Under appeal now
5 have been appealed at some point
Where they are
The map plots 47 projects on a background supplied by
OpenStreetMap , which receives your IP address when it loads.
The map needs JavaScript. Every project is listed in full below either way.
Positions are as published in the national planning register, or — for
applications made directly to An Coimisiun Pleanala — at the centre of the site boundary that
case publishes. Colour shows planning status.
Planning status
Planning status of renewable projects in South Dublin
Permission granted
36
Withdrawn
3
Permission lapsed
3
No decision recorded
5
Technologies
Technologies in the South Dublin pipeline
Solar
42
Battery storage
5
Wind
2
Grid infrastructure
1
A project appears under each technology it includes, so co-located
solar-and-battery schemes are counted in both.
Grid capacity
29 of 47 projects
are matched to a named substation with enough confidence to publish the link
(61.7%). The remaining 18 are
listed as unmatched rather than guessed — matching a project to the wrong substation is worse
than leaving it unmatched, so a name match must also be corroborated by distance before it counts.
0 projects sit at a substation ESB Networks
currently publishes as having no firm generation capacity available.
Areas
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the
large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as
they move through planning, and which substations still have capacity to take a connection. If you
want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the
areas you name.
No lease rates or valuations are published here, and nothing on this
site is an offer or a recommendation.
Live applications
Permission granted
Dublin 22 Capacity not stated 42.97 ha site Lodged Nov 15, 2017
Ref SD17A/0406
Grid: COOKSTOWN (110 kV), 1.29 km away.
14.2 MW of firm generation capacity available at BELGARD.
Permission granted
Dublin 22 Capacity not stated 16.23 ha site Lodged Feb 1, 2021
Ref SD20A/0283
Grid: CORKAGH (110 kV), 0.12 km away.
62.1 MW of firm generation capacity available at GRANGE CASTLE.
Permission granted
Dublin 22 Capacity not stated 16.23 ha site Lodged May 27, 2026
Ref SD20A/0283/EP
Grid: CORKAGH (110 kV), 0.12 km away.
62.1 MW of firm generation capacity available at GRANGE CASTLE.
Permission granted
Dublin 22 Capacity not stated 15.6 ha site Lodged Jun 9, 2025
Ref SDZ24A/0029W
Grid: BALGADDY (38 kV), 0.69 km away.
12.2 MW of firm generation capacity available at BALGADDY.
Permission granted
Dublin 24 Capacity not stated 13.672464688727501 ha site Lodged Aug 2, 2011
Ref SD118/0004
Grid: WHITESTOWN (38 kV), 0.81 km away.
12.4 MW of firm generation capacity available at WHITESTOWN.
Permission granted
Dublin 22 Capacity not stated 9.3 ha site Lodged Jun 26, 2006
Ref SD06A/0527
Grid: KILMAHUD (110 kV), 0.39 km away.
62.1 MW of firm generation capacity available at GRANGE CASTLE.
Permission granted
Newcastle Capacity not stated 8.2 ha site Lodged Oct 13, 2020
Ref SD20A/0058
Grid: KILMAHUD (110 kV), 1.04 km away.
ESB Networks has not published available generation capacity for KILMAHUD.
Permission granted
Dublin 24 Capacity not stated 6.8261444386837 ha site Lodged Jan 6, 2023
Ref LRD23A/0001
Grid: CITYWEST (110 kV), 0.24 km away.
30.6 MW of firm generation capacity available at CITYWEST.
Permission granted
Newcastle Capacity not stated 6.69 ha site Lodged Jul 11, 2023
Ref SD23A/0012
Grid: KILMAHUD (110 kV), 1.32 km away.
ESB Networks has not published available generation capacity for KILMAHUD.
Permission granted
Saggart Capacity not stated 6.37881655820701 ha site Lodged Dec 5, 2023
Ref SD23A/0100
Grid: SAGGART (38 kV), 1.37 km away.
5.5 MW of firm generation capacity available at SAGGART.
Permission granted
Dublin 24 Capacity not stated 6.3439 ha site Lodged Aug 23, 2022
Ref SD22A/0124
Grid: WHITESTOWN (38 kV), 1.05 km away.
26.4 MW of firm generation capacity available at FORTUNESTOWN.
Permission granted
Rathcoole Capacity not stated 5.807 ha site Lodged Oct 3, 2008
Ref SD08A/0684
Grid: SAGGART (38 kV), 2.39 km away.
5.5 MW of firm generation capacity available at SAGGART.
Permission granted
Dublin 22 Capacity not stated 5.18 ha site Lodged Oct 6, 2023
Ref SDZ22A/0018
Grid: CLONDALKIN (38 kV), 1.26 km away.
28 MW of firm generation capacity available at CLONDALKIN.
Permission granted
Dublin 22 Capacity not stated 4.87 ha site Lodged Dec 20, 2018
Ref SD18A/0447
Grid: CLONDALKIN (38 kV), 0.61 km away.
28 MW of firm generation capacity available at CLONDALKIN.
Permission granted
Dublin 22 Capacity not stated 4.519 ha site Lodged May 21, 2004
Ref SD03A/0838
Grid: YELLOWMEADOWS (110 kV), 0.47 km away.
28 MW of firm generation capacity available at CLONDALKIN.
Permission granted
Dublin 16 Capacity not stated 4.5 ha site Lodged Apr 24, 2019
Ref SD19A/0144
Grid: BALLYBODEN (38 kV), 1.8 km away.
8.9 MW of firm generation capacity available at BALLYBODEN.
Permission granted
Dublin 16 Capacity not stated 4.5 ha site Lodged Jun 19, 2020
Ref SD20A/0146
Grid: BALLYBODEN (38 kV), 1.8 km away.
8.9 MW of firm generation capacity available at BALLYBODEN.
Permission granted
Dublin 24 Capacity not stated 4.435 ha site Lodged Dec 21, 2016
Ref SD16A/0451
Grid: WHITESTOWN (38 kV), 0.28 km away.
12.4 MW of firm generation capacity available at WHITESTOWN.
Permission granted
Dublin 16 Capacity not stated 4.1 ha site Lodged Jun 19, 2006
Ref SD06A/0503
Grid: BALLYBODEN (38 kV), 3.77 km away.
8.9 MW of firm generation capacity available at BALLYBODEN.
Permission granted
Dublin 22 Capacity not stated 4.07 ha site Lodged Mar 23, 2020
Ref SD20A/0082
Grid: CORKAGH (110 kV), 0.5 km away.
ESB Networks has not published available generation capacity for CORKAGH.
Permission granted
Rathcoole Capacity not stated 3.96 ha site Lodged Jul 30, 2019
Ref SD19A/0240
Grid: SAGGART (38 kV), 2 km away.
5.1 MW of firm generation capacity available at KILTEEL.
Permission granted
Lucan Capacity not stated 3.77 ha site Lodged Aug 21, 2020
Ref SDZ20A/0008
Grid: ADAMSTOWN (110 kV), 0.75 km away.
24.5 MW of firm generation capacity available at ADAMSTOWN.
Permission granted
Dublin 24 Capacity not stated 3.71 ha site Lodged Nov 6, 2015
Ref SD15A/0150
Grid: OLDBAWN (38 kV), 1.89 km away.
10.4 MW of firm generation capacity available at OLDBAWN.
Permission granted
Dublin 22 Capacity not stated 3.228 ha site Lodged Jul 14, 2025
Ref SD25A/0097W
Grid: KILMAHUD (110 kV), 0.23 km away.
62.1 MW of firm generation capacity available at GRANGE CASTLE.
Permission granted
Rathcoole Capacity not stated 3.14 ha site Lodged Oct 6, 2021
Ref SD21A/0276
Grid: SAGGART (38 kV), 2.46 km away.
5.5 MW of firm generation capacity available at SAGGART.
Permission granted
Dublin 24 Capacity not stated 2.9 ha site Lodged Oct 11, 2022
Ref SD22A/0299
Grid: FORTUNESTOWN (110 kV), 0.43 km away.
26.4 MW of firm generation capacity available at FORTUNESTOWN.
Permission granted
Dublin 24 Capacity not stated 2.836 ha site Lodged Sep 15, 2023
Ref SD23A/0227
Grid: CITYWEST (110 kV), 0.63 km away.
30.6 MW of firm generation capacity available at CITYWEST.
Permission granted
Aerodrome Business Park Capacity not stated 2.72 ha site Lodged Apr 4, 2025
Ref SD25A/0008
Grid: SAGGART (38 kV), 2.1 km away.
5.5 MW of firm generation capacity available at SAGGART.
Permission granted
Dublin 22 Capacity not stated 2.65 ha site Lodged Feb 25, 2022
Ref SD21A/0186
Grid: BARNAKYLE (110 kV), 0.61 km away.
28 MW of firm generation capacity available at CLONDALKIN.
Permission granted
Adjoining Lands Capacity not stated 2.56 ha site Lodged Dec 21, 2023
Ref LRD23A/0014
Grid: BALLYBODEN (38 kV), 0.85 km away.
8.9 MW of firm generation capacity available at BALLYBODEN.
Permission granted
Clondalkin Capacity not stated 2.4 ha site Lodged Jun 20, 2022
Ref SD22A/0280
Grid: LIFFEY VALLEY (38 kV), 0.48 km away.
13.3 MW of firm generation capacity available at LIFFEY VALLEY.
Permission granted
Dublin 12 Capacity not stated 2.4 ha site Lodged Nov 19, 2025
Ref SD25A/0139W
Grid: GREENHILLS (38 kV), 0.36 km away.
9.1 MW of firm generation capacity available at GREENHILLS.
Permission granted
Dublin 22 Capacity not stated 2.32 ha site Lodged Mar 12, 2026
Ref SD25A/0301W
Grid: YELLOWMEADOWS (110 kV), 0.16 km away.
28 MW of firm generation capacity available at CLONDALKIN.
Permission granted
Dublin 24 Capacity not stated 2.21355884284061 ha site Lodged Jul 5, 2018
Ref SD188/0003
Grid: COOKSTOWN (110 kV), 0.57 km away.
67.6 MW of firm generation capacity available at COOKSTOWN.
Permission granted
Newcastle Capacity not stated 2.01 ha site Lodged Dec 20, 2024
Ref SD24A/0224W
Grid: KILMAHUD (110 kV), 0.84 km away.
62.1 MW of firm generation capacity available at GRANGE CASTLE.
Permission granted
Dublin 22 Capacity not stated 0.08 ha site Lodged May 19, 2023
Ref SD23A/0035
Grid: BARNAKYLE (110 kV), 0.29 km away.
ESB Networks has not published available generation capacity for BARNAKYLE.