Solar, wind and battery applications in the planning register for Ballylongford and the townlands around it, with the nearest substation and the capacity it has available. Last checked Sep 1, 2026.

7
Projects here
1
Still live
not refused, withdrawn or lapsed
Not stated
Capacity
no application here states a figure in MW
239.8
Hectares of site area
across 7 applications

The map plots 7 projects on a background supplied by OpenStreetMap, which receives your IP address when it loads.

Planning status

Planning status near Ballylongford Application submitted 1 Permission refused 2 Permission lapsed 4

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.

Every application here

Battery storage — Ballylongford

Application submitted Capacity not stated51.38 ha siteLodged May 20, 2025 Ref ABP-322568
Grid: MONEYPOINT (400 kV), 3.51 km away. ESB Networks has not published available generation capacity for MONEYPOINT.

Wind — Ballylongford

Permission lapsed Capacity not stated111.7 ha siteLodged Nov 17, 2017 Ref 171146
Grid: DROMBEG (110 kV), 5.22 km away. ESB Networks has not published available generation capacity for DROMBEG.

Battery storage — Ballylongford

Permission refused Capacity not stated51.38 ha siteLodged Aug 27, 2021 Ref ABP-311233
Grid: MONEYPOINT (400 kV), 3.51 km away. ESB Networks has not published available generation capacity for MONEYPOINT.

Wind — Ballylongford

Permission refused Capacity not stated19.88 ha siteLodged Sep 12, 2017 Ref 17902
Grid: DROMBEG (110 kV), 5.83 km away. ESB Networks has not published available generation capacity for DROMBEG.

Wind — Ballylongford

Permission lapsed Capacity not stated4.052 ha siteLodged Jul 7, 2017 Ref 17654
Grid: DROMBEG (110 kV), 5.22 km away. ESB Networks has not published available generation capacity for DROMBEG.

Wind — Ballylongford

Permission lapsed Capacity not stated0.96 ha siteLodged Apr 18, 2017 Ref 17339
Grid: KILPADDOGE (220 kV), 5.22 km away. 1.3 MW of firm generation capacity available at KILPADDOGE.

Wind — Ballylongford

Permission lapsed Capacity not stated0.4 ha siteLodged May 22, 2017 Ref 17466
Grid: KILPADDOGE (220 kV), 2.96 km away. 1.3 MW of firm generation capacity available at KILPADDOGE.

Areas are derived from the address as published by the planning authority or, for a direct application, by An Coimisiun Pleanala. A project on the boundary between two places may appear under either.