Wind at Ballylongford

MEELCON AND GURTEENAVALLIG , BALLYLONGFORD , CO KERRY

Permission lapsed
Planning status
Not stated
Capacity
the application states no figure in MW
0.4
Site area (hectares)
Wind
Technology

Grid

Nearest substation: KILPADDOGE (220 kV), 2.96 km away.
Association: No confident match to a named grid station.
Available capacity: 1.3 MW of firm generation capacity available at KILPADDOGE.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedMay 22, 2017
Decision dueJul 16, 2017
Decision madeJul 14, 2017
Permission grantedAug 17, 2017
Permission expiresAug 16, 2022
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Kerry County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.