Renewable energy projects near Dunleer

Solar, wind and battery applications in the planning register for Dunleer and the townlands around it, with the nearest substation and the capacity it has available. Last checked Sep 1, 2026.

5
Projects here
1
Still live
not refused, withdrawn or lapsed
16.0
MW stated
from 4 applications that state one
53.9
Hectares of site area
across 4 applications

The map plots 5 projects on a background supplied by OpenStreetMap, which receives your IP address when it loads.

Planning status

Planning status near Dunleer Permission granted 1 Permission refused 2 Permission lapsed 1 No decision recorded 1

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.

Every application here

Solar — Dunleer

Permission granted 4.0 MW statedLodged Dec 18, 2023 Ref 23483
Grid: DUNLEER (38 kV), 0.66 km away. 0.1 MW of firm generation capacity available at DUNLEER.

Solar — Dunleer

No decision recorded Capacity not stated13.47 ha siteLodged Mar 10, 2017 Ref 17179
Grid: DUNLEER (38 kV), 0.69 km away. 0.1 MW of firm generation capacity available at DUNLEER.

Solar — Dunleer

Permission lapsed 4.0 MW stated13.47 ha siteLodged May 5, 2017 Ref 17332
Grid: DUNLEER (38 kV), 0.7 km away. 0.1 MW of firm generation capacity available at DUNLEER.

Solar — Dunleer

Permission refused 4.0 MW stated13.47 ha siteLodged Jan 17, 2022 Ref 2226
Grid: DUNLEER (38 kV), 0.69 km away. 0.1 MW of firm generation capacity available at DUNLEER.

Solar — Dunleer

Permission refused 4.0 MW stated13.47 ha siteLodged May 27, 2022 Ref 22421
Grid: DUNLEER (38 kV), 0.69 km away. 0.1 MW of firm generation capacity available at DUNLEER.

Areas are derived from the address as published by the planning authority or, for a direct application, by An Coimisiun Pleanala. A project on the boundary between two places may appear under either.

← All of County Louth