Solar at Celbridge

Killeenlea Ardrass Lower & Killadoon , Celbridge , Co.Kildare

Permission lapsed
Planning status
Not stated
Capacity
the application states no figure in MW
47.44
Site area (hectares)
Solar
Technology

Grid

Nearest substation: GRIFFINRATH (110 kV), 1.49 km away.
Association: Matched to CELBRIDGE on place name and proximity (2.72 km).
Available capacity: 2.6 MW of firm generation capacity available at CELBRIDGE.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedMar 12, 2018
Further information requestedMay 4, 2018
Further information receivedDec 7, 2018
Decision dueJan 12, 2019
Decision madeJan 11, 2019
Appeal submittedFeb 6, 2019
Appeal decidedNov 13, 2019
Permission expiresNov 12, 2024
DecisionCONDITIONAL
Appeal reference303636-19
Appeal decisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Kildare County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.