Solar at Clonmel

Horsepasture/Doon , Clonmel , Co. Tipperary

Permission granted
Planning status
11.188
Capacity
as stated in the application
Not published
Site area (hectares)
Solar
Technology

Grid

Nearest substation: DOON (110 kV), 0.82 km away.
Association: Matched to DOON on place name and proximity (0.82 km).
Available capacity: No firm generation capacity currently available at DOON.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedJul 21, 2021
Further information requestedSep 9, 2021
Further information receivedOct 11, 2021
Decision dueNov 7, 2021
Decision madeNov 4, 2021
Permission grantedDec 8, 2021
Permission expiresDec 7, 2026
DecisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Tipperary County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.