Wind at Donegal Po

MASSLOUGHDERRYDUFF LACKAGHATERMON , ARDARA , DONEGAL PO

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
15.05
Site area (hectares)
Wind
Technology

Grid

Nearest substation: LOUGHDERRYDUFF (38 kV), 0.87 km away.
Association: Nothing states a connection point and the place name does not match a station, but LOUGHDERRYDUFF is only 0.87 km away — close enough that it is usually, though not always, where a project like this connects. Counted separately from the match rate.
Available capacity: ESB Networks has not published available generation capacity for LOUGHDERRYDUFF.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedAug 19, 2022
Decision dueOct 13, 2022
Decision madeOct 13, 2022
Appeal submittedNov 9, 2022
Appeal decidedSep 18, 2023
Permission expiresSep 17, 2028
DecisionREFUSED
Appeal referenceABP-315071-22
Appeal decisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Donegal County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.