Battery storage + Wind at Dublin 4
Poolbeg Generating Station, Pigeon House Road, Dublin 4
Grid
Association: The application names POOLBEG as its connection point.
Available capacity: 281.1 MW of firm generation capacity available at POOLBEG.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | Oct 23, 2020 |
|---|---|
| Further information requested | Dec 17, 2020 |
| Further information received | Mar 15, 2021 |
| Decision due | May 7, 2021 |
| Decision made | May 7, 2021 |
| Permission granted | Jun 22, 2021 |
| Decision | GRANT PERMISSION |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Dublin City Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.