Solar at Listowel

LISTOWEL , CO KERRY

Permission granted
Planning status
Not stated
Capacity
the application states no figure in MW
84.0
Site area (hectares)
Solar
Technology

Grid

Nearest substation: DROMBEG (110 kV), 4.84 km away.
Association: No confident match to a named grid station.
Available capacity: ESB Networks has not published available generation capacity for DROMBEG.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedApr 28, 2021
Further information requestedJun 21, 2021
Further information receivedOct 26, 2021
Decision dueNov 22, 2021
Decision madeNov 22, 2021
Permission grantedMay 19, 2022
Appeal submittedDec 20, 2021
Appeal decidedMay 19, 2022
Permission expiresMay 18, 2027
DecisionREFUSED
Appeal referenceABP -312288-21
Appeal decisionCONDITIONAL

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Kerry County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.