Solar at Rhode
CLONIN , RHODE , CO OFFALY
Grid
Association: Nothing states a connection point and the place name does not match a station, but DERRYIRON is only 1 km away — close enough that it is usually, though not always, where a project like this connects. Counted separately from the match rate.
Available capacity: ESB Networks has not published available generation capacity for DERRYIRON.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | Apr 30, 2019 |
|---|---|
| Decision due | Jun 24, 2019 |
| Decision made | Jun 21, 2019 |
| Appeal submitted | Jul 17, 2019 |
| Appeal decided | Mar 11, 2021 |
| Permission expires | Mar 10, 2031 |
| Decision | REFUSED |
| Appeal reference | 304925-19 |
| Appeal decision | CONDITIONAL |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Offaly County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.