Solar at Rosslare

BALLYCARRAN, ROSSLARE

Permission lapsed
Planning status
Not stated
Capacity
the application states no figure in MW
Not published
Site area (hectares)
Solar
Technology

Grid

Nearest substation: KILLINICK (38 kV), 1.45 km away.
Association: Nothing states a connection point and the place name does not match a station, but KILLINICK is only 1.45 km away — close enough that it is usually, though not always, where a project like this connects. Counted separately from the match rate.
Available capacity: 2.7 MW of firm generation capacity available at KILLINICK.

A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.

Planning timeline

Application lodgedJan 8, 2016
Decision dueMar 3, 2016
Decision madeFeb 26, 2016
Permission grantedMar 31, 2016
Permission expiresMar 30, 2021
DecisionGranted (Conditional)
Appeal decisionn/a

Source

Planning data: national planning register (ArcGIS IrishPlanningApplications), Wexford County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.