Solar at Thurles
Cooleeney and Derryfadda , Moyne , Thurles Co. Tipperary
Grid
Association: Nothing states a connection point and the place name does not match a station, but LISHEEN is only 1.24 km away — close enough that it is usually, though not always, where a project like this connects. Counted separately from the match rate.
Available capacity: 20.5 MW of firm generation capacity available at LISHEEN.
A nearest substation is a measurement of distance, not a statement of where this project will connect. Where a link is published it is because the application names the station, or because the project's own place name matches it and the two are close enough for that to mean something.
Planning timeline
| Application lodged | May 19, 2021 |
|---|---|
| Decision due | Jul 13, 2021 |
| Decision made | Jul 12, 2021 |
| Permission granted | Aug 13, 2021 |
| Permission expires | Aug 12, 2026 |
| Decision | CONDITIONAL |
What we have seen change
- — status: granted → lapsed
Recorded by this tracker each time the register was checked. It begins when we first observed the application, not when the application was made.
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Tipperary County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.