Planning timeline
| Application lodged | Jul 29, 2022 |
|---|---|
| Further information requested | Sep 22, 2022 |
| Further information received | Dec 5, 2022 |
| Decision due | Aug 24, 2023 |
| Decision made | Aug 24, 2023 |
| Appeal submitted | Sep 18, 2023 |
| Appeal decided | Jun 26, 2024 |
| Permission expires | Jun 25, 2029 |
| Decision | CONDITIONAL |
| Appeal reference | ABP-318041-23 |
| Appeal decision | CONDITIONAL |
Source
Planning data: national planning register (ArcGIS IrishPlanningApplications), Offaly County Council. Grid capacity: ESB Networks published capacity data. Retrieved Sep 1, 2026.
Register entry: council planning file.
Own land near one of these?
We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.
Email us to be added to the list — we will only use it to send project alerts for the areas you name.
No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.