Renewable energy projects in County Waterford

Every solar, wind and battery application in the county's planning register, joined to the ESB Networks substation nearest it and the generation capacity that substation has available. Updated from public records; last checked Sep 1, 2026.

Enter an Eircode, or a town, village or townland name. Only the routing key — the first three characters — is used and it is never stored: that places you within a few kilometres of your town, which is all this needs, and Eircode's full address database is licensed and not public anyway. All 139 routing keys in the country are covered.

65
Utility-scale projects
solar, wind and battery
30
Still live in the system
not refused, withdrawn or lapsed
683.2
MW stated
from 10 of 65 applications that state one
2643.8
Hectares of site area
across 48 applications
30
Substations with no capacity
of 64 near these projects
1
Under appeal now
14 have been appealed at some point

Where they are

The map plots 65 projects on a background supplied by OpenStreetMap, which receives your IP address when it loads.

Positions are as published in the national planning register, or — for applications made directly to An Coimisiun Pleanala — at the centre of the site boundary that case publishes. Colour shows planning status.

Planning status

Planning status of renewable projects in County Waterford Application submitted 4 Under appeal 1 Permission granted 25 Permission refused 2 Withdrawn 5 Permission lapsed 7 No decision recorded 21

Technologies

Technologies in the County Waterford pipeline Solar 39 Battery storage 17 Wind 16

A project appears under each technology it includes, so co-located solar-and-battery schemes are counted in both.

Grid capacity

30 of 65 projects are matched to a named substation with enough confidence to publish the link (46.2%). The remaining 35 are listed as unmatched rather than guessed — matching a project to the wrong substation is worse than leaving it unmatched, so a name match must also be corroborated by distance before it counts.

44 projects sit at a substation ESB Networks currently publishes as having no firm generation capacity available.

Areas

Own land near one of these?

We track every solar, wind and battery application in the national planning register — and the large ones made directly to An Coimisiun Pleanala, which never reach a council register at all — as they move through planning, and which substations still have capacity to take a connection. If you want to be told when something is lodged near your land, leave an email address.

Email us to be added to the list — we will only use it to send project alerts for the areas you name.

No lease rates or valuations are published here, and nothing on this site is an offer or a recommendation.

Live applications

Wind — Broemountain

Application submitted BroemountainCapacity not stated437.54 ha siteLodged Jul 7, 2026 Ref ABP-324420
Grid: KILCLOHER (38 kV), 8.13 km away. No firm generation capacity currently available at KILCLOHER.

Wind — Tooranaraheen

Application submitted TooranaraheenCapacity not stated427.95 ha siteLodged Dec 19, 2024 Ref ABP-321522
Grid: KILCLOHER (38 kV), 8.18 km away. No firm generation capacity currently available at KILCLOHER.

Solar — Ballyneal

Permission granted BallynealCapacity not stated141.0 ha siteLodged Mar 10, 2023 Ref 2360089
Grid: DEERPARK (38 kV), 6.96 km away. 0.6 MW of firm generation capacity available at DEERPARK.

Wind — Dungarvan

Permission granted DungarvanCapacity not stated106.8 ha siteLodged Mar 9, 2026 Ref 2660139
Grid: WOODHOUSE (110 kV), 1.4 km away. ESB Networks has not published available generation capacity for WOODHOUSE.

Solar — Hacketstown

Under appeal HacketstownCapacity not stated43.6 ha siteLodged Sep 15, 2025 Ref 2560648
Grid: CULLENAGH (220 kV), 2.33 km away. ESB Networks has not published available generation capacity for CULLENAGH.

Wind — Dungarvan

Permission granted DungarvanCapacity not stated15.23 ha siteLodged Sep 8, 2023 Ref 2360416
Grid: WOODHOUSE (110 kV), 0.34 km away. ESB Networks has not published available generation capacity for WOODHOUSE.

Solar — Tramore

Permission granted TramoreCapacity not stated12.0 ha siteLodged Oct 17, 2023 Ref 2360483
Grid: TRAMORE (38 kV), 2.48 km away. No firm generation capacity currently available at TRAMORE.

Solar — Dungarvan

Permission granted DungarvanCapacity not stated10.87 ha siteLodged Sep 19, 2023 Ref 2360433
Grid: KILCLOHER (38 kV), 2.1 km away. No firm generation capacity currently available at DUNGARVAN.

Solar — Kilmacthomas

Permission granted KilmacthomasCapacity not stated10.2 ha siteLodged Jul 21, 2023 Ref 2360317
Grid: KILMACTHOMAS (38 kV), 0.97 km away. No firm generation capacity currently available at KILMACTHOMAS.

Solar — Knockhouse Lower Waterford

Permission granted Knockhouse Lower WaterfordCapacity not stated7.348 ha siteLodged Feb 20, 2024 Ref 2460080
Grid: KILLOTERAN (110 kV), 0.69 km away. 28.2 MW of firm generation capacity available at KILLOTERAN.

Solar — Knockhouse Lower Waterford

Permission granted Knockhouse Lower WaterfordCapacity not stated7.348 ha siteLodged Nov 28, 2024 Ref 2460721
Grid: KILLOTERAN (110 kV), 0.69 km away. 28.2 MW of firm generation capacity available at KILLOTERAN.

Battery storage — Lahardan

Permission granted LahardanCapacity not stated5.45 ha siteLodged Apr 5, 2024 Ref 2460163
Grid: CULLENAGH (220 kV), 1.01 km away. ESB Networks has not published available generation capacity for CULLENAGH.

Solar — Dungarvan

Permission granted DungarvanCapacity not stated5.3 ha siteLodged Aug 17, 2023 Ref 2360374
Grid: SPRINGS (38 kV), 0.53 km away. No firm generation capacity currently available at DUNGARVAN.

Solar — Waterford City

Permission granted Waterford CityCapacity not stated4.24 ha siteLodged Jun 19, 2023 Ref 2360261
Grid: WATERFORD IND EST (38 kV), 1.46 km away. No firm generation capacity currently available at WATERFORD IND EST.

Solar — Monamintra

Permission granted MonamintraCapacity not stated3.59 ha siteLodged Sep 11, 2024 Ref 2460522
Grid: KILCARAGH (38 kV), 0.69 km away. ESB Networks has not published available generation capacity for KILCARAGH.

Solar — Kilbarry Ballynaneashagh

Application submitted Kilbarry BallynaneashaghCapacity not stated3.4 ha siteLodged Aug 27, 2026 Ref 2660654
Grid: WATERFORD IND EST (38 kV), 1.22 km away. No firm generation capacity currently available at WATERFORD IND EST.

Battery storage — Kilmeaden

Application submitted KilmeadenCapacity not stated2.49 ha siteLodged Dec 5, 2025 Ref 2560872
Grid: CULLENAGH (220 kV), 0.12 km away. No firm generation capacity currently available at KILMEADEN.

Solar — Ballymacarbry

Permission granted BallymacarbryCapacity not stated2.3 ha siteLodged May 27, 2024 Ref 2460286
Grid: SPA ROAD (38 kV), 9.27 km away. No firm generation capacity currently available at SPA ROAD.

Solar — Kill

Permission granted KillCapacity not stated2.15 ha siteLodged Feb 1, 2024 Ref 2460051
Grid: KILMACTHOMAS (38 kV), 7.88 km away. No firm generation capacity currently available at KILMACTHOMAS.

Solar — Portlaw

Permission granted PortlawCapacity not stated2.0 ha siteLodged Jul 26, 2022 Ref 22669
Grid: PORTLAW (38 kV), 3.32 km away. No firm generation capacity currently available at PORTLAW.

Battery storage + Solar — Dungarvan

Permission granted Dungarvan5.0 MW stated1.26 ha siteLodged Oct 4, 2024 Ref 2460589
Grid: DUNGARVAN (110 kV), 0.16 km away. No firm generation capacity currently available at DUNGARVAN.

Solar — Kilmacthomas

Permission granted KilmacthomasCapacity not stated0.31 ha siteLodged Jul 21, 2023 Ref 2360316
Grid: KILMACTHOMAS (38 kV), 0.57 km away. No firm generation capacity currently available at KILMACTHOMAS.

Solar — Knockhouse Lower Waterford

Permission granted Knockhouse Lower WaterfordCapacity not stated0.108 ha siteLodged Jun 6, 2025 Ref 2560399
Grid: KILLOTERAN (110 kV), 0.45 km away. 28.2 MW of firm generation capacity available at KILLOTERAN.

Battery storage — Cork Road Waterford

Permission granted Cork Road Waterford1.0 MW stated0.011 ha siteLodged Nov 22, 2024 Ref 2460705
Grid: WATERFORD IND EST (38 kV), 0.46 km away. No firm generation capacity currently available at WATERFORD IND EST.

Solar — Ballygarron Upper

Permission granted Ballygarron UpperCapacity not stated0.01 ha siteLodged Aug 14, 2024 Ref 2460467
Grid: KILCARAGH (38 kV), 1.23 km away. ESB Networks has not published available generation capacity for KILCARAGH.

Solar — Dungarvan

Permission granted Dungarvan5.0 MW statedLodged Mar 10, 2017 Ref 17156
Grid: DUNGARVAN (110 kV), 0.27 km away. No firm generation capacity currently available at DUNGARVAN.

Battery storage + Solar — Tramore

Permission granted TramoreCapacity not statedLodged Aug 31, 2017 Ref 17645
Grid: TRAMORE (38 kV), 3.51 km away. No firm generation capacity currently available at TRAMORE.

Wind — Monageela/Killatoor

Permission granted Monageela/KillatoorCapacity not statedLodged Nov 13, 2020 Ref 20845
Grid: WOODHOUSE (110 kV), 1.41 km away. ESB Networks has not published available generation capacity for WOODHOUSE.

Solar — Kilcoher

Permission granted KilcoherCapacity not statedLodged Jul 29, 2021 Ref 21735
Grid: KILCLOHER (38 kV), 4.05 km away. No firm generation capacity currently available at KILCLOHER.

Wind — Dungarvan

Permission granted DungarvanCapacity not statedLodged May 13, 2022 Ref 22407
Grid: WOODHOUSE (110 kV), 4.49 km away. No firm generation capacity currently available at DUNGARVAN.